| SCHEMES UNDER ADDITIONAL CENTRAL ASSISTANCE (ACA) IN RESPECT OF PHED | |||||||
| Name of Department : Public health Engineering | |||||||
|
Sl. No. |
Name of Project | For which year | Project cost | Amount released (Rs. in crore) | Progress | Remarks | |
| Fianancial (Rs.in crore) up to July,12 | Physical (in percent) up to July, 12 | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Water Supply to New A.R. Complex at Zokhawsang | 2006-2007 | 1.00 | 1.00 | 1.00 | 100 | completed |
| 2 | Construction of Zonal Tank near Synod Conference Hall | 2006-2007 | 0.28 | 0.28 | 0.28 | 100 | completed |
| TOTAL | 1.28 | 1.28 | 1.28 | 100 | |||
| 3 | Integrated Project of Aizawl (IPA) Greater Aizawl Water Supply Scheme PH- II (State Share) | 2007-2008 | 15.00 | 15.00 | 15.00 | 100 | completed |
| 4 | Greater Champhai Water Supply Scheme (Supplementary Estimate) | 2007-2008 | 7.00 | 7.00 | 7.00 | 100 | completed |
| TOTAL | 22.00 | 22.00 | 22.00 | 100 | |||
| 5 | Spring water harvesting within Aizawl 'S' | 2008-2009 | 0.63 | 0.095 | 0.095 | 100 | completed |
| 6 | Construction of Reservoir and Extension of Gravity Main at Zuangtui | 2008-2009 | 0.49 | 0.315 | 0.315 | 100 | completed |
| 7 | Zemabawk Bethel Veng WSS | 2008-2009 | 0.25 | 0.17 | 0.17 | 100 | completed |
| 8 | Helipad Water Supply Scheme | 2008-2009 | 0.07 | 0.037 | 0.037 | 100 | completed |
| 9 | Procurement of Atomic absorption Spectrophotometer and construction of Room for Gas Chromotograph | 2008-2009 | 0.21 | 0.21 | 0.21 | 100 | completed |
| 10 | Restoration of Tuirial Jail WSS | 2008-2009 | 0.33 | 0.33 | 0.33 | 100 | completed |
| 11 | Improvement of Distribution System of GAWSS Ph-I | 2008-2009 | 0.70 | 0.70 | 0.70 | 100 | completed |
| 12 | W Serzawl (Imp)WSS | 2008-2009 | 0.16 | 0.024 | 0.024 | 100 | completed |
| 13 | Construction of RWHS at Thingsat & E.Damdiai | 2008-2009 | 0.29 | 0.0438 | 0.0438 | 100 | completed |
| 14 | Ratu (Pumping) WSS | 2008-2009 | 1.08 | 1.08 | 1.08 | 100 | completed |
| 15 | Borai (Aug) WSS | 2008-2009 | 0.52 | 0.15 | 0.15 | 100 | completed |
| 16 | Thaidawr- I WSS | 2008-2009 | 0.18 | 0.028 | 0.028 | 100 | completed |
| 17 | Dilzawl WSS | 2008-2009 | 0.27 | 0.041 | 0.041 | 100 | completed |
| 18 | Rajiv Nagar WSS | 2008-2009 | 0.83 | 0.83 | 0.83 | 100 | completed |
| 19 | Riangtlei WSS | 2008-2009 | 0.60 | 0.09 | 0.09 | 100 | completed |
| 20 | Hmuntha (Aug) WSS | 2008-2009 | 0.29 | 0.17 | 0.17 | 100 | completed |
| 21 | Sailulak (Imp) WSS | 2008-2009 | 0.24 | 0.14 | 0.14 | 100 | completed |
| 22 | Camp Veng (Hamlet of Thingsulthliah) WSS | 2008-2009 | 0.45 | 0.45 | 0.45 | 100 | completed |
| 23 | Improvement of Tlangpui WSS | 2008-2009 | 0.30 | 0.30 | 0.30 | 100 | completed |
| 24 | Sihpui Pumping Scheme at E.Lungdar | 2008-2009 | 0.43 | 0.43 | 0.43 | 100 | completed |
| 25 | Renewal of Greater Serchhip Water Supply Scheme. | 2008-2009 | 0.30 | 0.30 | 0.30 | 100 | completed |
| 26 | Vanbawng (Aug) WSS | 2008-2009 | 1.34 | 1.02 | 1.02 | 100 | completed |
| 27 | Ngaizawl WSS | 2008-2009 | 0.55 | 0.27 | 0.27 | 100 | completed |
| 28 | Neihdawn (Aug) WSS | 2008-2009 | 0.17 | 0.1 | 0.1 | 100 | completed |
| 29 | Vanchengpui (Aug) WSS | 2008-2009 | 0.34 | 0.26 | 0.26 | 100 | completed |
| 30 | Selam (Aug) WSS | 2008-2009 | 0.40 | 0.40 | 0.40 | 100 | completed |
| 31 | Murlen WSS | 2008-2009 | 0.68 | 0.08 | 0.08 | 100 | completed |
| 32 | Thekpui WSS | 2008-2009 | 0.40 | 0.03 | 0.03 | 100 | completed |
| 33 | New Hruaikawn WSS | 2008-2009 | 0.40 | 0.03 | 0.03 | 100 | completed |
| 34 | Khuangleng WSS | 2008-2009 | 0.86 | 0.06 | 0.06 | 100 | completed |
| 35 | Sesih WSS | 2008-2009 | 0.50 | 0.03 | 0.03 | 100 | completed |
| 36 | Bungzung WSS | 2008-2009 | 1.09 | 0.16 | 0.16 | 100 | completed |
| 37 | N.E.Diltlang WSS (Pumping) | 2008-2009 | 0.83 | 0.73 | 0.73 | 100 | completed |
| 38 | Vapar (Aug) WSS | 2008-2009 | 0.48 | 0.33 | 0.33 | 100 | completed |
| 39 | Thekte (Aug) WSS | 2008-2009 | 0.35 | 0.35 | 0.35 | 100 | completed |
| 40 | Marpara 'S' WSS | 2008-2009 | 0.32 | 0.23 | 0.23 | 100 | completed |
| 41 | Tawipui 'N'- I WSS | 2008-2009 | 0.39 | 0.24 | 0.24 | 100 | completed |
| 42 | Lalnutui (Imp) WSS | 2008-2009 | 0.18 | 0.09 | 0.09 | 100 | completed |
| 43 | Sedailui WSS | 2008-2009 | 0.25 | 0.15 | 0.15 | 100 | completed |
| 44 | Sairep WSS | 2008-2009 | 0.23 | 0.12 | 0.12 | 100 | completed |
| 45 | Thangte WSS | 2008-2009 | 0.25 | 0.14 | 0.14 | 100 | completed |
| 46 | Dengsur (Aug) WSS | 2008-2009 | 0.25 | 0.25 | 0.25 | 100 | completed |
| 47 | S.Phaileng WSS (Replacement of Gravity & Distribution Pipeline) | 2008-2009 | 0.25 | 0.25 | 0.25 | 100 | completed |
| 48 | Ukdasuri WSS | 2008-2009 | 0.23 | 0.23 | 0.23 | 100 | completed |
| 49 | Hauruang WSS | 2008-2009 | 0.94 | 0.94 | 0.94 | 100 | completed |
| 50 | New Ngharchhip (Aug)WSS | 2008-2009 | 0.42 | 0.03 | 0.03 | 100 | completed |
| 51 | Tuipui 'D' | 2008-2009 | 0.27 | 0.27 | 0.27 | 100 | completed |
| 52 | Ngiautlang WSS | 2008-2009 | 0.10 | 0.05 | 0.05 | 100 | completed |
| 53 | Maniababsora-I (Aug) WSS | 2008-2009 | 0.23 | 0.12 | 0.12 | 100 | completed |
| 54 | Zochachhuah WSS | 2008-2009 | 0.13 | 0.08 | 0.08 | 100 | completed |
| 55 | Dumzau 'T' WSS | 2008-2009 | 0.22 | 0.22 | 0.22 | 100 | completed |
| 56 | Ulusury WSS | 2008-2009 | 0.21 | 0.12 | 0.12 | 100 | completed |
| 57 | Ngharum WSS | 2008-2009 | 0.28 | 0.28 | 0.28 | 100 | completed |
| 58 | Pelyabapsora WSS | 2008-2009 | 0.15 | 0.15 | 0.15 | 100 | completed |
| 59 | Silbanga WSS | 2008-2009 | 0.12 | 0.12 | 0.12 | 100 | completed |
| 60 | Khamrang (Aug) WSS | 2008-2009 | 0.33 | 0.18 | 0.18 | 100 | completed |
| 61 | Zanlawn (Imp) WSS | 2008-2009 | 0.29 | 0.15 | 0.15 | 100 | completed |
| 62 | Saihapui 'V' (Aug) WSS | 2008-2009 | 0.20 | 0.20 | 0.20 | 100 | completed |
| 63 | Chite WSS | 2008-2009 | 0.21 | 0.21 | 0.21 | 100 | completed |
| 64 | Saiphai WSS | 2008-2009 | 0.30 | 0.30 | 0.30 | 100 | completed |
| 65 | Renewal of Greater Kolasib Water Supply Scheme. | 2008-2009 | 0.90 | 0.90 | 0.90 | 100 | completed |
| 66 | Ground Water Exploration using IM-III, IM-II HPTW & Submersible Pump | 2008-2009 | 2.90 | 2.90 | 2.90 | 100 | completed |
| 67 | Renewal of Pumping Machineries and Equiptment of Transmission System of GAWSS-Phase-I | 2008-2009 | 16.82 | 1.68 | 1.68 | 20 | on-going |
| 68 | Improvement of Intake arrangement of GAWSS Ph-I | 2008-2009 | 0.60 | 0.60 | 0.60 | 100 | completed |
| 69 | Renewal of Greater Lunglei Water Supply Scheme. | 2008-2009 | 1.20 | 1.20 | 1.20 | 100 | completed |
| TOTAL | 46.18 | 22.17 | 22.17 | 100 | |||