SALIENT FEATURES OF SOLAR WATER PUMPING SYSTEM AT BUANGPUI

 

1.         State                                                    :           Mizoram

 

2.         District                                                 :           Serchhip District

 

3.         River                                                    :           Vanva

 

4.         Population base year                          :           2011 AD

 

5.         Population Design year                      :           2041 AD

 

6.         Design period                                      :           30 years

 

7.         Design population                               :           959 souls (ultimate)

 

8.         Water supply level 

            (Before commissioning)                      :           22.69 lpcd

 

9.         Design supply level                             :           55 lpcd

 

10.       No. of target habitation                       :           1 village

 

11.       Intake structures                                 :           RCC weir 

 

12.       Method of water treatment                  :           a) Sedimentation

                                                                                    b) Horizontal Roughing Filter.

 

13.       Size and length of gravity main          :           125mm ø GI - 850Rm

 

14.       Nos of pumping stages                       :           1 (one)

 

15.       Static head                                          :           85m

 

16.       Size and length of pumping main       :           65mm ø GI - 1500Rm

                                    

17.       Length of approach road                    :           700 metres

 

18.       Nos of new reservoirs                         :           2 new reservoir (RCC Sump-I & II)

 

19.       Scope of work                                     :           Departmental/Contract

 

20.       Pump capacity                                    :           0.118 MLD

 

21.       Execution time                                    :           12 months

 

22.       Estimated Amount                              :           Rs.1,28,91,000.00                                          

                                                                                    (NABARD RIDF-XXI)

 

23.       Starting the Work                                :           10.03.2016

 

24.       Date of Commission                           :           27.03.2017

 

25.       Date of Completion                             :           30.03.2017

 

26.       FHTC under JJM (2019-2020)            :           108 House Hold