GREATER BAIRABI WATER SUPPLY SCHEME
• Location of the scheme : Bairabi
• Nature of scheme : Gravity
• Population : 3304 (2001 Census)
a) Initial stage : 3727
b) Intermediate stage : 5120
c) Ultimate stage : 7454
• Total quantity of water produced
a) Initial stage : 0.167 mld
b) Intermediate : 0.230 mld
c) Ultimate : 0.335 mld
• Rate of Supply : 70 lpcd
• Present Rate of Supply : 45 lpcd
• Source : Thuampuilui=2.272 lps
Biakhluna Vaului=0.757lps
Vankhuma Lui =(2.25+ 2.27) = 4.52 lps
• Discharge : 7.549 lps
• Static Head : Thuampuilui = 30 m
Biakhluna Vaului=20m
Vankhuma Lui = 50m and 58 m
• Terminal Head : Thuampuilui = 8.68 m
Biakhluna Vaului= 12.85m
Vankhuma Lui = 6.02 m and 31.27 m
• Estimate cost : Rs.77,54,000/-
• Per capita cost : Rs.1040/-
• Year of commencement : 2001 AD• Year of completion : 2002 AD
• No. of house connection : 90
• Percentage population coverage : 64%
• Funding pattern : ARWSP
• Agency for implementation : PHED
Page Links: https://phed.mizoram.gov.in/page/greater-bairabi-water-supply-schemep
GREATER BAIRABI WATER SUPPLY SCHEME
Department Updates Title
- NOTIFICATION - EE, AWTD, PHED to take charge of SDO, AWT Sub-Div Dt. 28.2.2025
- Certificate of Transfer of Charge of Superintendent, E-in-C Office, PHED Dt. 25.2.2025
- Appointment of Nodal Officers for all Court Cases in PHE Department Dt. 28.2.2025
- Transfer and posting of Officers under PHE Department Dt. 21.2.2025
- Shifting of SDO-I&II Office under AWDD North Office at RWD, Aizawl Building, Lapuitlang
Government of Mizoram Latest News