GREATER SAIHA WATER SUPPLY SCHEME
• Location of the scheme : Saiha
• Nature of scheme : Gravity
• Population : 19826 (2001 Census)
a) Initial stage : 13659
b) Intermediate stage : 14877
c) Ultimate stage : 30000
• Total quantity of water produced
a) Initial stage : 0.273 mld
b) Intermediate : 0.297 mld
c) Ultimate : 0.600 mld
• Rate of Supply : 70 lpcd
• Present Rate of Supply : 20 lpcd
• Source & Discharge : 1. Zotlanglui-I = 0.43lps
2. Zotlanglui-II = 1.06 lps
3. Bawihtelui Upper = 0.99 lps
4. Bawihtelui Lower = 5.99 lps
5. Saihatlanglui = 8.00lps
6. Lakherchavalui = 1.00 lps
7. PHE Lui = 7.67 lps
• Static Head : 1. Zotlanglui-I = 23.75 m
2. Zotlanglui - II = 101.75m
3. Bawihtelui Upper = 20m
4. Bawihtelui Lower = 79.20m
5. Saihatlanglui = 40.08 m
6. Lakherchavalui = 11.76m
7. PHE Lui = 56.13 m
• Terminal Head : Saihatlanglui = 2.00 m
PHE Lui = 26.87 m
Bawihtelui = 5.863 m
Lakherchavalui = 2.50 m
• Estimate cost : Rs.3,98,00,000/-
• Per capita cost : Rs.1327/-
• Year of commencement : 1994 AD
• Year of completion : 1999-2000
• No. of house connection : 1210
• Percentage population coverage : 29%
• Funding pattern : 100% State
• Agency per implementation : PHED
Page Links: https://phed.mizoram.gov.in/page/greater-saiha-water-supply-schemep
GREATER SAIHA WATER SUPPLY SCHEME
Department Updates Title
- Regularisation Order - Electrician-II, LDC and Store Keeper
- Condonation of Overage - Regularization of Provisional Employees Scheme, 2020 Dt. 5.11.2024
- Study leave granted to Er.Lalawmpuia, SDO, Kawrthah WATSAN Sub-Division Dt.10/10/2024
- Repatriation order of Er.Lalthanzuali Dt.25/09/2024
- Confirmation of Plumbers Dt.17/09/2024
Government of Mizoram Latest News