GREATER SERCHHIP WATER SUPPLY SCHEME
• Location of the scheme : Serchhip
• Nature of scheme : Pumping
• Population : 25000 (Design)
a) Initial stage : 13680
b) Intermediate stage : 19340
c) Ultimate stage : 25000
• Total quantity of water produced
a) Initial stage : 0.40 mld
b) Intermediate : 1.00 mld
c) Ultimate : 1.60 mld
• Rate of Supply as per Norm : 70 lpcd
• Present Rate of Supply : 70 lpcd
• Source : River Tuikum
• Discharge : 40 lps
• Static Head : 454 m
• Total Head : 480 m
• Estimate cost : Rs.11,20,00,000/-
• Per capita cost : Rs.4480/-
• Year of commencement : 1993
• Year of completion : 1997
• No. of house connection : 1195
• Percentage population coverage : 100%
• Funding pattern : 100% State
• Implementing Agency : JEP & PHED
Page Links: https://phed.mizoram.gov.in/page/greater-serchhip-water-supply-schemep
GREATER SERCHHIP WATER SUPPLY SCHEME
Department Updates Title
- Condonation of Over-aged Contract JE regularization - regarding Dt. 17.12.2024
- Regularization of JE engaged on Contract basis to post of JE under PHED Dt. 17.12.2024
- Promotion of Pu F. Lalfakawma, Senior Grade of MES to Junior Administrative Grade of MES (Non-functional) Dt. 12.12.2024
- Transfer Kept in Abeyance until further orders Dt. 6.12.2024
- Regularization Order - SA, Pump Operator, Welder
Government of Mizoram Latest News