NABARD RIDF XV to RIDF XVII ( Kum 2009-2010 atanga 2012-2013 ) thlenga achievement leh proposal | ||||||
B : COMPLETED SCHEMES : | ||||||
STATUS OF WORKS OF DRINKING WATER SUPPLY UNDER NABARD RIDF-XV | ||||||
Sl. No. |
Name of Project |
Approved cost estimate |
Up to date Expenditure | Physical achievement in % | Remarks | |
1 |
Water Supply to New Capital Complex, Khatla |
127.61 | 127.61 | 100 |
1. Amount of loan sanctioned by NABARD vide No. NB(Miz.)/1780/RIDF-XV(RR)/2009-10 Dt. 29.1.2010 is Rs. 1031.24 lakh out of Total Outlay of Rs. 1145.83 lakh 2. All the schemes are fully completed physically and financially. |
|
2 | Chhuarlung Water Supply Scheme | 219.62 | 219.62 | 100 | ||
3 |
Improvement of Champhai Water Supply Scheme |
394.60 | 394.60 | 100 | ||
4 |
Construction of Rain Water Harvesting Tank at Saitual |
205.00 | 205.00 | 100 | ||
5 |
Construction of Rain Water Harvesting Tank at K_ilung |
199.00 | 199.00 | 100 | ||
TOTAL | 1145.83 | 1145.83 | 100 | |||
STATUS OF WORKS OF DRINKING WATER SUPPLY UNDER NABARD RIDF-XVI | ||||||
1 | Khawpuar RWHS | 84.24 | 84.24 | 100 | Financially and physically completed | |
2 | Lungpho RWHS | 100.00 | 100.00 | 100 | ||
3 | Vaseitlang-I WSS | 49.42 | 49.42 | 100 | ||
4 | Bualpui H WSS | 42.00 | 42.00 | 100 | ||
5 | S. Mualcheng RWHS | 61.23 | 61.23 | 100 | ||
6 | Moraicherra WSS | 78.07 | 78.07 | 100 | ||
7 | W Lungdar RWHS | 91.96 | 91.96 | 100 | ||
8 | Vangtlang RWHS | 106.12 | 106.12 | 100 | ||
9 | Construction of Durtlang WSS | 341.93 | 341.93 | 100 | ||
TOTAL | 954.97 | 954.97 | 100 | |||
B : ON-GOING SCHEMES : | ||||||
STATUS OF WORKS OF DRINKING WATER SUPPLY UNDER NABARD RIDF-XVII | ||||||
1 | Bawngthah WSS | 102.74 | 70.00 | 67% | Some Schemes are physically completed but all the Schemes are financially incompleted. During 2012-2013 a fund of Rs. 170.00 lakh and Rs. 19.00 lakh are earmartked under NABARD share & Staate Share respectively. | |
2 |
Chamring (Aug.) WSS |
82.70 | 74.43 | 70% | ||
3 | Leisenzo WSS | 128.92 | 74.02 | 70% | ||
4 |
S.Vnalaiphai WSS (Replacement) |
43.11 | 38.80 | 90% | ||
5 | M.Kawnpui WSS | 68.16 | 61.34 | 100% | ||
6 | Thlengang WSS | 41.23 | 37.11 | 100% | ||
7 |
Chalrang (Imp.) WSS |
103.38 | 70.00 | 70% | ||
8 | Tualpui (Imp) WSS | 93.46 | 84.11 | 50% | ||
9 | Haulawng Pumping WSS | 355.50 | 100.00 | 36% | ||
10 | New Ahmepy WSS | 70.10 | 63.09 | 100% | ||
11 | Siata WSS | 49.58 | 44.62 | 100% | ||
12 | Lungtian-II WSS | 77.20 | 69.48 | 80% | ||
1216.076 | 787.00 |