1 | Location of the Scheme | : S.Khawbung |
2 | Nature of Scheme | : Pumping |
3 | Population | |
a) Initial Stage | : 4730 souls | |
b) Intermediate Stage | : 5416 souls | |
c) Ultimate Stage | : 5566 souls | |
4 | Total Quantity of Water produced | |
a) Initial Stage | 0.48 MLD | |
b) Intermediate Stage | 0.56 MLD | |
c) Ultimate Stage | 0.64 MLD | |
5 | Rate of Supply | : 70% of the population - 70lpcd 30% of the population- 40 lpcd |
6 | Present Rate of Supply | : 70 lpcd |
7 | Source | : Tuipui River |
8 | Discharge | : 78 lps |
9 | Static Head | : 50 m |
10 | Total Head | : 950 m |
11 | Estimate Cost | : Rs. 8,27,38,000.00 |
12 | Per capita cost | : 14864.89 |
13 | Year of Commencement | : 2013 AD |
14 | Year of Completion | : 2019 AD |
15 | No. of House Connection | : 62 nos |
16 | Percentage Population Coverage | : 100% |
17 | Funding Pattern | : NLCPR (DoNER) |
18 | Implementing Agency | : PHED |