1Location of the Scheme: S.Khawbung
2Nature of Scheme: Pumping
3Population

a) Initial Stage: 4730 souls

b) Intermediate Stage: 5416 souls

c) Ultimate Stage: 5566 souls
4Total Quantity of Water produced

a) Initial Stage0.48 MLD

b) Intermediate Stage0.56 MLD

c) Ultimate Stage0.64 MLD
5Rate of Supply: 70% of the population - 70lpcd
   30% of the population- 40 lpcd
6Present Rate of Supply: 70 lpcd
7Source: Tuipui River
8Discharge: 78 lps
9Static Head: 50 m
10Total Head: 950 m
11Estimate Cost: Rs. 8,27,38,000.00
12Per capita cost: 14864.89
13Year of Commencement: 2013 AD
14Year of Completion: 2019 AD
15No. of House Connection:  62 nos
16Percentage Population Coverage: 100%
17Funding Pattern: NLCPR (DoNER)
18Implementing Agency: PHED