THENZAWL GREATER WATER SUPPLY SCHEME
• Location of the scheme : Thenzawl
• Nature of scheme : Gravity Scheme
• Population : 5607 (2001 Census)
a) Initial stage : 4502
b) Intermediate stage : 5607
c) Ultimate stage : 9891
• Total quantity of water produced
a) Initial stage : 0.515 mld
b) Intermediate : 0.392 mld
c) Ultimate : 0.692 mld
• Rate of Supply : 70 lpcd
• Present Rate of Supply : 70 lpcd
• Source : Charpui Lui and
Phulkawn Lui
• Discharge : 3.00 lps and 1.66 lps
• Static Head : 53 m and 331 m
• Terminal Head : 18.90 m and 15.828 m
• Estimate cost : Rs.1,46,45,000/-
• Per capita cost : Rs.1481/-
• Year of commencement : 1999 AD
• Year of completion : 11.3.2002
• No. of house connection : 147
• Percentage population coverage : 100%
• Funding pattern : 50 : 50 AUWSP : State
• Implementing Agency : PHED
Page Links: https://phed.mizoram.gov.in/page/thenzawl-greater-water-supply-schemep
THENZAWL GREATER WATER SUPPLY SCHEME
Department Updates Title
- Office Order - Condonation of Overaged for 3 Provisional Employees Dt. 28.3.2025
- Regularization Order, 1 DEO and 2 LDC_
- Engagement of PE converted to Contract basis under PHED Dt. 27.3.2025
- Notification - Placement of Er. Lalhruaitluanga, SDO in the functional post of Senior Grade (Executive Engineer) under PHED Dt. 26.3.2025
- Promotion of Er.H.Lallianmawia, Sr. Executive Engineer to Superintending Engineer under PHED Dt. 26.3.2025
Government of Mizoram Latest News