TLABUNG WATER SUPPLY SCHEME (Aug.)
• Location of the scheme : Tlabung
• Nature of scheme : Gravitation
• Population : 3681 (2001 Census)
a) Initial stage : 1200
b) Intermediate stage : 1400
c) Ultimate stage : 1680
• Total quantity of water produced
a) Initial stage : 0.042 mld
b) Intermediate : 0.049 mld
c) Ultimate : 0.059 mld
• Rate of Supply as per Norm : 70 lpcd
• Present Rate of Supply : 35 lpcd
• Source : Zohmunlui
• Discharge : 0.533 lps
• Static Head : 120 m
• Available Head : 48.50 m
• Estimate cost : Rs.8,29,00,000/-
• Per capita cost : Rs.5314/-
• Year of commencement : 1999 AD
• Year of completion : 2002 AD
• No. of house connection : 191
• Percentage population coverage : 50%
• Funding pattern : ARWSP
• Implementing Agency : PHED
Page Links: https://phed.mizoram.gov.in/page/tlabung-water-supply-scheme-aug-p
TLABUNG WATER SUPPLY SCHEME (Aug.)
Department Updates Title
- Pi Ngursangzuali Sailo, Under Secretary, PHED as State Asst. Public Information Officer (SAPIO) Dt. 16.4.2025
- Er. Vanlalthlengliana, SDO to take charge of SDO (power), AWTD under PHED Dt. 11.4.2025
- Appointment for Ezra Vanmalsawma to the post of Junior Grade of MES under PHED Dt. 11.4.2025
- Public Notice - 2nd Pumbling Licence Examination, 2025
- Office Order - Posting of Stenographer Grade-II under PHED Dt, 9.4.2025
Government of Mizoram Latest News